Al Shaqab Equestrian Centre
- Project: Al Shaqab Equestrian Centre
- Client: Zublin international
- Location: Education city
Equipment/Machines used:
Trucks, lifting gears, mobile cranes, scaffolding, excavators, telehandlers, forklifts, man lifts, scissors lifts, tower lights and Generators.
Scope of work:
In the final preparations for the 2022 world cup various buildings had to be demolished in a short time frame, these ranged from steel-structured buildings to concrete structures. All the buildings had to be fully demolished, and the area was fully cleared/leveled.
How the work was executed:
The steel structure buildings had to be taken apart piece by piece so they could be placed in storage and re-erected later. This was done with a combination of man lifts, cranes and dismantling equipment.
The other structures were demolished using diamond-cutting machines such as floor saws and excavators. All waste material was removed from the site and the area was made good again.